Pančevo 208MW gas power plant

1/7/2016
Project development

€ 180 million

$ 195.624 million

Announced

1/7/2016


Overview:

  • Pančevo 208MW gas power plant.
  • Tsentrenergoholding (a Gazprom subsidiary) and NIS Novi Sad have established project company Serbskaya Generaciya Novi Sad, to develop a new combined cycle gas fired power plant in Pančevo.
  • Tsentrenergoholding will own 51% of the project company with NIS Novi Sad taking a 49% stake.
  • Metka is acting as EPC contractor on the project.
  • The electricity produced will fuel a nearby refinery and petrochemical complex.
  • The agreements were signed in 2013 with construction set to begin in 2017.

Sam Duke - Editor

Jurisdiction:

Serbia

Deal type:

Project development

Practice area:

Project development

Industry sector:

Energy


Firm:

Party: Metka (EPC contractor)