Toruń 330MW gas power plant

1/4/2017
Project development, Project finance

€ 130 million

$ 141.380 million

Completed

1/4/2017


Overview:

  • Toruń 330MW gas power plant.
  • EDF Polska and a fund managed by Polskie Inwestycje Rozwojowe (now Polish Development Fund - PFR) are financing the development of a new power and heat plant at Toruń.
  • The plant is expected to be in commission in the first half of 2017. 
  • The fund managed by PIR is called FIIK (Kapitałowy Fundusz Inwestycyjny Zamknięty Aktywów Niepublicznych) and will become part of a SPV which EDF Polska has established.  
  • It will cost about Zl550 million to construct the new plant and PIR will provide Zl275 million of this from the Inwestycje Polskie fund.

Rani Mehta - Journalist 

Jurisdiction:

Poland

Deal types:

Project development
Project finance

Practice areas:

Project finance
Project development

Governing law:

Poland

Industry sector:

Energy


Firms:

Party: EDF Polska (Lender)


Party: Polskie Inwestycje Rozwojowe (Lender)

Lawyer: Artur Jonczyk