Kariba South hydroelectric power plant extension (300MW)

1/12/2016
Project development, Project finance

$ 500 million

Announced

1/12/2016


Overview:

  • Kariba South hydroelectric power plant extension (300MW).
  • The project will add 300MW to the existing 750MW power plant at Kariba.
  • Zimbabwe Power Company has signed an EPC agreement with Sinohydro who are developing the project.
  • Standard Bank is acting as arranger on $120 million of financing to be used both for this project and the rehabilitation of the Hwange plant.
  • The first phase 150MW is expected to be complete by 2017 with the second phase due for completion in 2018.
  • The original plant had been built in 1962 with a capacity of 666MW before expanding to 750MW.

Sam Duke - Editor

Jurisdiction:

Zimbabwe

Deal types:

Project development
Project finance

Practice areas:

Project finance
Project development

Governing laws:

England and Wales
Zimbabwe

Industry sector:

Energy


Firms:

Party: Standard Bank of South Africa (Arranger)

Party: PTA Bank (Lender)


Party: Zimbabwe Power Company (Sponsor)

Lawyer: Sue Brighton


Party: Zimbabwe Power Company (Sponsor)


Party: Standard Bank of South Africa (Arranger)

Party: PTA Bank (Lender)